For more project information on the European Commision's website - click here

Project Highlights

​

278 multi-standard fast chargers (50 kW)

in Germany (241), Belgium (37)

in cooperation with sister-project Fast-E SK/CZ

 

10 partners with a budget of  17.6 M € and 50% CEF grant 

 

Action duration: 4 years, September 2014 – September 2018

 

7 out of 9 TEN-T Core Network Corridors are electrified

 

Types of partners: OEMs, energy companies, railway company, charge point operator, distribution service operator

​

More info: https://www.allego.eu/

NRD_6454_edited.jpg

Role of Ardan

​

Application writing and support in building a consortium of partners

------------------------------------------------------------------------------------------

Project Management and quarterly Steering Committees meeting

------------------------------------------------------------------------------------

Preparing annual Actual Status Report

--------------------------------------------------

Co-organising of dissemination events and tools

---------------------------------------------------------------

Study for Market Integration and Innovative Business Orientation

---------------------------------------------------------------------------------------

Study for Innovative ICT Solutions

---------------------------------------------

Preparing EV Roll-out Master Plan and Final Technical Report

---------------------------------------------------------------------------------

Grant Agreement, Consortium Agreement, project extension support

------------------------------------------------------------------------------------------

Network planning

------------------------

​

​