Project Highlights
2,146 recgarching points for LDV (150-300 kW) and 128 recharching points for HDV (350 kW) in 461 locations
along the Core Network and Comprehensive Network across 23 Member States in Europe - CZ, EL, HU, HR, LT, LV, PL, RO, SK, SL, AT, BE, DE, DK, EE, ES, FI, FR, IE, IT, NL, PT and SE.
6 partners with a budget of more than 230 M € and
CEF grant of more than 70 M €
Action duration: 3 years, June 2022 - November 2025
9 out of 9 TEN-T Core Network Corridors are electrified.
Types of partners: Charge Point Operator/ CPO (Ionity, Greenway, Renovatio, Fortisis), energy (Grid Telecom) and retail (KESCO/KAuto)
![Bild2.png](https://static.wixstatic.com/media/281986_90d5a6af15ea46cfaf3ba09d4a561dc5~mv2.png/v1/crop/x_0,y_12,w_735,h_828/fill/w_473,h_533,al_c,q_85,usm_0.66_1.00_0.01,enc_avif,quality_auto/Bild2.png)
![Saint-Witz_85A0498[31573].jpg](https://static.wixstatic.com/media/281986_49bcf737d59f4e208369396bf39e68bb~mv2.jpg/v1/crop/x_0,y_895,w_5100,h_1610/fill/w_982,h_310,al_c,q_80,usm_0.66_1.00_0.01,enc_avif,quality_auto/Saint-Witz_85A0498%5B31573%5D.jpg)
Role of Ardan
​
Application writing and support in building a consortium of partners
------------------------------------------------------------------------------------------
Project Management and quarterly Steering Committees meetings
--------------------------------------------------------------------------------------
Financial support incl. submission of Interim Payments & Final Report
--------------------------------------------------------------------------------------------
Co-organising of dissemination events and tools
---------------------------------------------------------------
Supporting interoperable roaming solutions
-------------------------------------------------------
Monitoring and risk management
---------------------------------------------